2014 Capital Projects Levy

The Columbia Heights Public Schools community passed a new 10-year Capital Projects Levy Nov. 4, 2014 allowing this District to work on much-needed capital projects. The voter-approved Capital Project Levy provides $10 million over a decade, starting with Fiscal Year 2016 (July 1, 2015 to June 30, 2016). During this timeframe, this District will invest approximately $1 million annually into facilities (60 percent) and technology (40 percent).

Each year District administrators will report out to the School Board and community the status of the facilities and technology projects funded by the 2014 Capital Projects Levy. In addition to reporting out to the School Board, the District will include 2014 Capital Project Levy information in applicable district publications and provide updates with the support of the news media. Please use this page and links to learn more about how Columbia Heights Public Schools is investing in facilities and technology, all of which will help create worlds of opportunity for every learner.

Leading up to the 2014 Capital Project Levy, Columbia Heights Public Schools provided factual information to the community as to how the District would invest taxpayer's monies each fiscal year. The following charts, updated annually, reflect what the District reported it would do in terms of facilities (60 percent) and technology (40 percent). The charts below show the projects, by fiscal year, and their status.

Fiscal Year* 2016 Facilities Planned/Completed Projects

Status

Fiscal Year 2016 Technology Planned/Completed Projects

Status

Parking/Drive improvements - Highland Elementary School, District Center, Columbia Heights High School  Completed Purchased, inventoried and initial levy funded distribution of student devices and tools - 5th and 8th grades Completed
Brick tuck-pointing study - Columbia Academy  Completed Network infrastructure upgrading - CA & NPES Completed
Replacing main entry windows - Columbia Heights High School  Completed Staff Development - Districtwide Completed
Replacing and/or repairing roofs, windows, doors, plumbing and casework  Ongoing Increasing Internet bandwidth Completed 
Replacing or repairing furnaces and boilers - Columbia Heights High School Deferred Improving parent and student portal technology systems Completed 
Resurfacing athletic track - Columbia Heights High School Completed Increasing technology systems for safety and security Completed 
Improving signage - Columbia Heights High School, Highland Elementary School Completed Installing, replacing, supporting and maintaining software Completed 

Fiscal Year* 2017 Facilities Planned/Completed Projects

Status

Fiscal Year* 2017 Technology Planned/Completed Projects

Status

Parking/Drive/entrance and exit improvements - Valley View Elementary School Completed Personalized Learning Initiative expansion
(4th through 9th grades)
Completed
Brick tuck-pointing, Columbia Academy Completed  Purchasing additional student devices Completed
Cold Water Repiping - Columbia Heights High School Completed  Network infrastructure upgrades - Columbia Heights High School and Highland Elementary School Completed
Improving signage - Valley View Elementary School Completed  Classroom technology upgrades - Districtwide Completed
    Staff Development - Districtwide Completed

Fiscal Year* 2018
facilities projects

Status 

Fiscal Year* 2018
technology projects

Status

Replacing windows at Columbia Academy Completed Expanding networks and infrastructure capacity
for wireless access - Valley View
Completed 
Replacing domestic water lines (Phase 1) - Columbia Heights High School  Completed Classroom technology upgrades - Districtwide  Ongoing
    Personalized Learning Initiative expansion
(4th through 11th grades)
Completed
    Professional Development Staffing Support Ongoing

Fiscal Year* 2018-2019
facilities projects

   

Fiscal Year* 2018-2019
Technology projects

 
Replacing boilers - Highland Elementary School Completed Technology integration staff person to support the expansion of technology in instruction Continuing
Replacing domestic water lines (Phase II), Columbia Heights High School Completed Increase professional development programming Continuing
    Expanding 1 to 1 Chromebooks for grades 4-12 Completed
    Increase technology hardware (supporting infrastructure
equipment and classroom technology)
Continuing

* Fiscal Year: July 1 through June 30.

This District also contributed existing funds toward Capital Facility projects. The following charts shows capital projects, by Fiscal Year, not funded by the 2014 Capital Projects Levy. 

Fiscal Year 2016 Projects

Facility

Status

Secure front entry (Audio visual remote system) North Park Elementary School Completed
Broken steam pipe repair Highland Elementary School Completed 
New windows Columbia Heights High School Completed 
Remodel old kindergarten rooms Valley View Elementary School Completed
Update signage District Center, Highland Elementary School,
Columbia Heights High School
Completed 

Fiscal Year 2017 Projects

Facility

Status

Performance studio build-out Columbia Heights High School  Completed
Update signage Valley View Elementary School  Completed
Repair Parking District Center, Columbia Heights High School  Completed
Replace upper windows and doors Highland Elementary School  Completed
Carpet classroom Columbia Heights High School Ongoing
Kitchen flooring Columbia Heights High School Completed

Fiscal Year 2018 Projects

Facility

Status

Purchase two vans Districtwide Completed
District Center maintenance and replacement District Center Completed
Playground Valley View Elementary School Completed
Band Instruments Districtwide Ongoing


Presentations
View the Sep. 29, 2014 PowerPoint presentation.
View the Feb. 10, 2015 PowerPoint presentation
View the April 26, 2016 School Board PowerPoint presentation.
View the Jan. 10, 2017 PowerPoint presentation.
View the April 25, 2017 School Board PowerPoint presentation.
View the April 24, 2018 School Board PowerPoint presentation.